PRINCE2 Foundation — Question 125
How is the benefits management approach used in the 'closing a project process?
Answer options
- A. To assess any benefits that have already been realized
- B. To ensure that the customer can support the products when the project is disbanded
- C. To capture side effects identified during post project benefits reviews
- D. To verify user acceptance of the project's product
Correct answer: A
Explanation
The correct answer is A because the benefits management approach focuses on assessing the benefits that have been realized by the project, ensuring that stakeholders understand the success achieved. Options B and D are related to customer support and user acceptance but do not pertain specifically to the assessment of realized benefits. Option C, while relevant to post-project activities, does not directly address the assessment of benefits achieved during the closing phase.