PRINCE2 Foundation — Question 124
Which of the following statements about lines of authority and reporting are true?
1. The Project Manager has day-to-day control for a management stage within the limits laid down by the Project Board.
2. If a Team Manager forecasts a deviation beyond Work Package tolerances, this should be referred to the Project Manager.
Answer options
- A. Only 1 is true
- B. Only 2 is true
- C. Both 1 and 2 are true
- D. Neither 1 or 2 are true
Correct answer: C
Explanation
Statement 1 is correct because the Project Manager indeed has day-to-day oversight during a management stage as per the Project Board's limits. Statement 2 is also accurate since any significant deviations beyond Work Package tolerances must be escalated to the Project Manager for proper management.