PRINCE2 Foundation — Question 114
How should the 'managing product delivery' process be used?
Answer options
- A. As a way of obtaining project acceptance from the project board
- B. As an alternative to using the PRINCE2 quality review technique
- C. As an interface to third party suppliers that are not using PRINCE2
- D. As a way to allow team managers to create their own work packages
Correct answer: B
Explanation
The correct answer is B because the 'managing product delivery' process serves as a substitute for the PRINCE2 quality review technique, ensuring that quality is maintained without duplicating efforts. Option A is incorrect as it does not focus on quality management, C is not relevant as it pertains to supplier interactions, and D is not correct since it does not align with the structured approach of PRINCE2.