PRINCE2 Foundation — Question 112

Which process plans the activities of the 'closing a project' process?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the process of 'Closing a project' specifically focuses on planning and executing the necessary activities to finalize the project. The other options, such as 'Managing a stage boundary', 'Directing a project', and 'Starting up a project', pertain to different aspects of project management and do not relate directly to the closing activities.