PRINCE2 Foundation — Question 111

Which should be provided by corporate or programme management before the Starting up a Project process commences?

Answer options

Correct answer: B

Explanation

The correct answer, B, indicates that corporate or program management needs to provide enough information to recognize the potential Executive before starting the project. The other options, while important, pertain to different aspects of project initiation and are not prerequisites for starting the process.