PRINCE2 Foundation — Question 109
Which is an objective of the 'closing a project' process?
Answer options
- A. To provide corporate management with an interface to the project
- B. To ensure the project's delivery will be within set tolerances
- C. To seek approval to replace the project or stage plan
- D. To assess the benefits that have already been realized
Correct answer: D
Explanation
The correct answer is D because assessing the benefits realized is a key objective in closing a project to understand its success. Options A, B, and C do not align with the primary purpose of project closure, which focuses on evaluating outcomes rather than management interfaces or planning adjustments.