PRINCE2 Foundation — Question 108
In a commercial environment, which process links the team manager and the PRINCE2 method used in a project?
Answer options
- A. Directing a project
- B. Managing product delivery
- C. Managing a stage boundary
- D. Initiating a project
Correct answer: B
Explanation
The correct answer is B, as 'Managing product delivery' is the process that ensures the team manager is effectively coordinating the delivery of project outputs in accordance with the PRINCE2 framework. Options A, C, and D are related processes that do not specifically focus on the link between the team manager and the execution of project deliverables.