PRINCE2 Foundation — Question 106
Which is NOT a purpose of the Initiating a Project process?
Answer options
- A. Enable a Project Board decision about the commitment of resources to a project
- B. Enable an organization to understand the work that needs to be done to deliver a project's products before a project is approved
- C. Establish solid foundations for a project
- D. Enable the Project Board to decide whether it is worthwhile to initiate a project
Correct answer: D
Explanation
The correct answer is D because the Initiating a Project process does not focus on deciding the worthiness of starting a project; rather, it is about preparing for the project's launch. Options A, B, and C all accurately describe purposes of the Initiating a Project process, emphasizing resource commitment, understanding project scope, and establishing a strong project base.