PRINCE2 Foundation — Question 105

How is the tailoring approach defined for a project?

Answer options

Correct answer: A

Explanation

The correct answer is A because it is the responsibility of the project board to approve the tailoring approach to ensure it aligns with project objectives. Option B is incorrect as documenting does not equate to approval. Options C and D incorrectly assign the approval and documentation responsibilities to project assurance, which is not their role in this context.