PRINCE2 Foundation — Question 105
How is the tailoring approach defined for a project?
Answer options
- A. The project board approves the approach
- B. The project board documents the approach
- C. Project assurance approves the approach
- D. Project assurance documents the approach
Correct answer: A
Explanation
The correct answer is A because it is the responsibility of the project board to approve the tailoring approach to ensure it aligns with project objectives. Option B is incorrect as documenting does not equate to approval. Options C and D incorrectly assign the approval and documentation responsibilities to project assurance, which is not their role in this context.