PRINCE2 Foundation — Question 101

When should the Project Board refer to corporate or programme management for a decision?

Answer options

Correct answer: B

Explanation

The correct answer, B, is accurate because exceeding project level tolerance is a significant issue that necessitates higher management involvement. Options A and C are more operational matters that can typically be managed within the project framework, while option D, while important, does not specifically indicate a need to escalate to corporate or programme management.