PRINCE2 Foundation — Question 101
When should the Project Board refer to corporate or programme management for a decision?
Answer options
- A. The stage requires resources
- B. It is forecast that project level tolerance will be exceeded
- C. The Senior Supplier or Senior User needs to be changed
- D. Any request for change needs to be approved
Correct answer: B
Explanation
The correct answer, B, is accurate because exceeding project level tolerance is a significant issue that necessitates higher management involvement. Options A and C are more operational matters that can typically be managed within the project framework, while option D, while important, does not specifically indicate a need to escalate to corporate or programme management.