PRINCE2 Foundation — Question 100

Which process covers the work done by external suppliers who may NOT be using PRINCE2?

Answer options

Correct answer: C

Explanation

The correct answer, C. Managing Product Delivery, focuses on ensuring that products are delivered as agreed, regardless of the methodologies used by external suppliers. The other options do not specifically address the involvement of external suppliers or their methodologies.