PRINCE2 Agile Foundation — Question 8
How is the 'tailor to suit the project' principle applied in an agile context?
Answer options
- A. By flexing what is produced to stay in control and deliver value
- B. By emphasizing tolerances on what is being delivered
- C. By using the Agilometer to assess the project environment
- D. By fitting releases into planned management stages
Correct answer: C
Explanation
The correct answer is C because the Agilometer is a tool specifically designed to gauge the project environment, which aligns with tailoring processes to fit specific project needs. The other options describe various agile practices but do not directly relate to the principle of customizing approaches based on project contexts.