PRINCE2 Agile Foundation — Question 32

Which statement about timeboxes is CORRECT?

Answer options

Correct answer: C

Explanation

The correct answer is C because a timebox can indeed encompass another timebox, allowing for nested time management. Option A is incorrect as flow-based working does not necessarily partition into timeboxes. Option B is false because projects can be treated as timeboxes, and option D is misleading since timeboxes can be beneficial even in routine business contexts.