PRINCE2 Agile Foundation — Question 32
Which statement about timeboxes is CORRECT?
Answer options
- A. Flow based working partitions work into timeboxes
- B. A project cannot be referred to as a timebox
- C. A timebox can contain another timebox
- D. Timeboxes should be avoided in business as usual environments
Correct answer: C
Explanation
The correct answer is C because a timebox can indeed encompass another timebox, allowing for nested time management. Option A is incorrect as flow-based working does not necessarily partition into timeboxes. Option B is false because projects can be treated as timeboxes, and option D is misleading since timeboxes can be beneficial even in routine business contexts.