Which role is responsible for facilitating the Agilometer assessment?
Answer options
- A. Project board
- B. Project manager
- C. Team manager
- D. Customer subject matter expert
Correct answer: B
Explanation
The Project manager is responsible for ensuring that assessments like the Agilometer are conducted effectively. The Project board oversees the project as a whole, while the Team manager focuses on team dynamics, and the Customer subject matter expert provides insights but does not facilitate the assessment.