Which statement about the ‘initiating a project’ process is CORRECT?
Answer options
- A. The initiation stage plan should form part of the project plan
- B. The impact of frequent releases on quality management should be assessed
- C. The process should take more time than usual for disruptive projects
- D. The project solution should be documented in detail in the project product description
Correct answer: A
Explanation
The correct answer is A because the initiation stage plan is indeed a critical component of the overall project plan. Option B is incorrect as it focuses on release impacts rather than initiation. Option C is misleading as the initiating process should not necessarily take more time for disruptive projects. Option D is also incorrect because the project product description should summarize the solution rather than document it in detail.