Which TWO project board responsibilities are specifically assigned to the senior user?
1. Demonstrating the achievement of benefits.
2. Specifying the needs of those impacted by the outputs.
3. Balancing business, user and supplier demands.
4. Ensuring that the project delivers value for money.
Answer options
- A. 1 and 2
- B. 2 and 3
- C. 3 and 4
- D. 1 and 4
Correct answer: A
Explanation
The senior user is primarily responsible for demonstrating the achievement of benefits and specifying the needs of those affected by the project's outputs. Options B, C, and D incorrectly include responsibilities that are generally associated with other roles on the project board, such as balancing demands and ensuring value for money, which are not specifically assigned to the senior user.