Project Management Professional (PMP) — Question 993

In the middle of an iteration, the product owner tells the agile team that the government has updated legal requirements. This will result in some changes in the product definition.

How should the project manager handle this situation?

Answer options

Correct answer: C

Explanation

The correct answer is C because the change in product definition necessitates a reassessment of the iteration backlog to ensure alignment with the new requirements. Options A and B do not address the need for immediate review, while option D incorrectly delegates the assessment to a business analyst instead of prioritizing the project manager's responsibility to reassess the backlog.