Project Management Professional (PMP) — Question 984

A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because performing a detailed assessment allows the project manager to understand the full implications of the requested change on the project timeline and resources. Answer A is incorrect as initiating a risk response strategy may not directly address the impact of the change. Answer C is not ideal since rejecting changes without assessment could overlook valuable stakeholder input. Answer D might be a possible solution, but it requires thorough evaluation before implementation.