Project Management Professional (PMP) — Question 984
A project is in the final stages, and a key stakeholder demands a change to a product feature that will add 2 weeks to the critical path. What should the project manager do?
Answer options
- A. Initiate a risk response strategy from the risk register.
- B. Perform a detailed assessment to analyze the impact.
- C. Reject the changes as the project is in the final stages.
- D. Use schedule compression methods to alter the critical path.
Correct answer: B
Explanation
The correct answer is B because performing a detailed assessment allows the project manager to understand the full implications of the requested change on the project timeline and resources. Answer A is incorrect as initiating a risk response strategy may not directly address the impact of the change. Answer C is not ideal since rejecting changes without assessment could overlook valuable stakeholder input. Answer D might be a possible solution, but it requires thorough evaluation before implementation.