Project Management Professional (PMP) — Question 981

An experienced project manager is working on a complex hybrid project that has several dependencies with other projects. How should the project manager reduce the risk related to those external dependencies?

Answer options

Correct answer: A

Explanation

The correct answer, A, emphasizes the importance of thoroughly evaluating the consolidated project plans to identify dependencies and ensure that they align with business value. Options B and D suggest delegating the responsibility for dependency evaluation, which may lead to oversight. Option C, while tracking progress is important, does not directly address the proactive assessment of dependencies.