A project manager is leading a project with several stakeholders in other functional areas of the company. One of these stakeholders has just been promoted to lead another functional area, and remains a stakeholder for this project.
What should the project manager have the project team update to ensure proper communications to stakeholders?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Stakeholder engagement plan, as it outlines how to communicate and engage with stakeholders throughout the project. Updating this plan ensures that the newly promoted stakeholder's role and interests are considered. The other options, while important, do not specifically focus on stakeholder communication and engagement strategies.