Project Management Professional (PMP) — Question 975

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because reviewing the new requirements with the compliance department is essential to determine if a formal change request is necessary, ensuring adherence to regulatory standards. Option B is incorrect as it risks non-compliance, while option C is unwise without proper assessment, and option D is not viable since ignoring regulatory changes can lead to significant legal and financial repercussions.