Project Management Professional (PMP) — Question 975
A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.
What should the project manager do next?
Answer options
- A. Review the new requirements with the compliance department to determine if a change request is needed
- B. Proceed with the defined project requirements and delay implementing the new requirements
- C. Add the new requirements to the project scope immediately since they are mandatory changes
- D. Ignore the new requirements as the current budget and schedule do not allow for any changes
Correct answer: A
Explanation
The correct answer is A because reviewing the new requirements with the compliance department is essential to determine if a formal change request is necessary, ensuring adherence to regulatory standards. Option B is incorrect as it risks non-compliance, while option C is unwise without proper assessment, and option D is not viable since ignoring regulatory changes can lead to significant legal and financial repercussions.