Project Management Professional (PMP) — Question 973

A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.

Which activity should the project manager undertake?

Answer options

Correct answer: D

Explanation

The correct answer is D because reviewing the definition of the minimum viable product (MVP) can help ensure that future deliveries meet the customer's expectations for business value. Options A, B, and C do not directly address the customer's concerns about perceived value in the delivered products.