Project Management Professional (PMP) — Question 973
A project delivers every 2 weeks. The customer raises a complaint because they do not perceive business value in the products delivered even though deliveries have been completed in a timely manner.
Which activity should the project manager undertake?
Answer options
- A. Change the delivery project approach.
- B. Review the risk analysis.
- C. Perform a cost-benefit analysis.
- D. Review the definition for the minimum viable product (MVP).
Correct answer: D
Explanation
The correct answer is D because reviewing the definition of the minimum viable product (MVP) can help ensure that future deliveries meet the customer's expectations for business value. Options A, B, and C do not directly address the customer's concerns about perceived value in the delivered products.