A project has come to a halt. What should the project manager do to get the project back on track?
Answer options
- A. Review the status of each blocker at the daily standup meeting.
- B. Create a Kanban board that describes each blocker.
- C. Create a radiator that places the blockers in a tabular format.
- D. Engage with the project team to understand the blockers.
Correct answer: D
Explanation
The correct answer is D because engaging with the project team allows the project manager to gain insights into the specific issues causing the delay. Options A, B, and C may provide visibility of the problems but do not directly address understanding the root causes of the blockers.