For the second time in a week, one of the team members failed to deliver their assigned work. As a result, it is impossible for the team to achieve their agreed-upon target.

What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because discussing the issue directly with the team member allows for understanding the reasons behind their failure to deliver and finding a solution collaboratively. Option A is incorrect as insisting on output without addressing the underlying issues may lead to further problems. Option B, while useful, does not address the immediate problem at hand. Option D may not be necessary if the root cause can be resolved with the current team member.