Project Management Professional (PMP) — Question 926
During the initiation stage of a multimedia exhibition-design project, the project manager is developing the project management plan. What should the project manager do to complete this task?
Answer options
- A. Initiate a survey to solicit end-customer opinions and prioritize exhibition contents.
- B. Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract.
- C. Benchmark other similar exhibitions' deliverable lists and final outcomes.
- D. Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.
Correct answer: D
Explanation
The correct answer, D, is essential because clarifying high-level business requirements helps establish a clear framework for the project's deliverables. Options A and C focus on gathering opinions or comparing with others, which are less critical at this stage. Option B addresses contractual issues but does not contribute to developing the project management plan.