Project Management Professional (PMP) — Question 902

A project team is performing extremely well when it comes to delivering the value-added features to the customer in each sprint. However, they are missing the documentation portion and the project manager must find a way to make sure the documentation is kept current.

Which action should the project manager take?

Answer options

Correct answer: D

Explanation

The correct answer is D because making documentation a standard part of the definition of done ensures that it is consistently addressed alongside feature delivery. Option A may not be effective if documentation is not integrated into the team's workflow. Option B might delay the project because it separates documentation from the regular sprint cycle. Option C risks leaving documentation incomplete and outdated.