Project Management Professional (PMP) — Question 899
An organization is transitioning to an agile project delivery approach. Each project is structured as a Scrum team. A project is in the initiation phase. In one of the workshops, a business subject matter expert (SME) indicated that the project may have legal constraints. The legal team was not identified as a stakeholder in the project brief.
What should the project lead do?
Answer options
- A. Ask the solutions architect to contact the legal department and create the epic(s) in the product backlog.
- B. Advise the SME that there are no legal requirements identified in the project brief and continue the workshop.
- C. Ask the project sponsor to contact the legal department and identify the legal impact.
- D. Add the legal department to the list of stakeholders and contact them to discuss the project scope.
Correct answer: D
Explanation
The correct answer is D because involving the legal department is crucial to ensure any legal constraints are addressed early in the project. Options A and C do not directly involve the legal department as stakeholders, and option B dismisses the SME's concerns, which could lead to significant issues later in the project.