Project Management Professional (PMP) — Question 898
A project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference. What can the project manager do to improve interactions between the team members in both countries?
Answer options
- A. Identify virtual communication methods and arrange for regular team meetings accordingly.
- B. Plan for frequent face-to-face meetings.
- C. Explore the opportunity to have both teams collocated.
- D. Ensure full participation of both the product owner and business SMEs in scope planning sessions.
Correct answer: A
Explanation
The correct answer is A because identifying virtual communication methods and scheduling regular meetings can bridge the gap created by the time difference. Options B and C are impractical due to the geographical separation and time constraints, while D addresses participation but does not specifically improve interactions across the time zones.