Project Management Professional (PMP) — Question 898

A project team consists of members based in country A and subject matter experts (SMEs) based in country B with a 12-hour time difference. What can the project manager do to improve interactions between the team members in both countries?

Answer options

Correct answer: A

Explanation

The correct answer is A because identifying virtual communication methods and scheduling regular meetings can bridge the gap created by the time difference. Options B and C are impractical due to the geographical separation and time constraints, while D addresses participation but does not specifically improve interactions across the time zones.