Project Management Professional (PMP) — Question 882
An agile senior project team member suddenly resigns from the organization. Following this departure, the remaining team members are having difficulty accessing information and are unable to complete a deliverable.
What should the project manager have done to avoid this situation?
Answer options
- A. Ensured the project repository is up to date.
- B. Made an effort to reemploy the senior project team member.
- C. Updated the job descriptions for all team roles.
- D. Provided specialist training for all team members.
Correct answer: A
Explanation
The correct answer, A, emphasizes the importance of maintaining an up-to-date project repository to ensure all team members can access necessary information. Option B is not a viable solution as reemploying the individual isn't always possible. Option C, while useful for clarity in roles, does not directly address the issue of information access. Option D may enhance skills but does not resolve the immediate problem of accessing the needed information.