Project Management Professional (PMP) — Question 859

A pharmacy needs to launch a medication delivery service. An interdisciplinary team was created in order to have the service ready in one-month when it usually takes five months to complete.

What should the project manager do?

Answer options

Correct answer: C

Explanation

The correct answer is C because proposing a minimum viable product (MVP) allows the team to focus on essential features that can be delivered quickly. Options A and B do not directly address the urgency of the timeline, while D may not be feasible if team capacity cannot be increased rapidly.