Project Management Professional (PMP) — Question 853

A project manager is leading a multiyear project. Near the end of the first year, the project manager checks to see if the whole budget allocated for the year will be used. Some features utilizing this year's budget were added later in the year as change requests, but these features will not be ready by the end of the first year.

What should the project manager do?

Answer options

Correct answer: D

Explanation

The correct answer is D because providing an update to the financial department about the project's timeline is essential for budget management and future planning. Options A and B are incorrect because they suggest authorizing payments for features that are not fully ready, which is not a proper financial practice. Option C is also not appropriate as creating a nonbinding contract without fixed deliverables could lead to confusion and mismanagement of resources.