A customer is unhappy after weeks of working in a newly implemented virtual environment and wants their key stakeholders to be more involved in the development processes. The customer is requesting access to the information radiators of the project management information system (PMIS). The development company has never allowed clients access to the system.

What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B, as identifying the root causes of the customer's dissatisfaction is essential for addressing their concerns effectively. Options A and D do not address the customer's issues directly, while C may overlook the opportunity to understand the client's perspective and improve the relationship.