Project Management Professional (PMP) — Question 846

A project manager is leading an agile project in an organization that has not executed this type of project before. In order to ensure the project is following the compliance requirements, what should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because collaborating with the PMO or compliance entity ensures that the agile processes are tailored to meet compliance requirements effectively. Option A is incorrect as it focuses on documentation rather than proactive compliance integration. Option C compromises the agile project's performance for adherence to outdated processes, while option D wrongly suggests bypassing compliance requirements instead of integrating them.