Project Management Professional (PMP) — Question 845
A project manager has been assigned to a new project. The project schedule is extremely short. During an iteration review meeting. the key stakeholder mentions that they are experiencing some inefficiencies in their work processes.
What should the project manager do?
Answer options
- A. Perform a schedule impact analysis with the team.
- B. Ask the team to evaluate their process
- C. Review deliverables with the key stakeholder.
- D. Seek support from the project sponsor.
Correct answer: B
Explanation
The correct answer is B because asking the team to evaluate their process allows for immediate identification and resolution of inefficiencies. A schedule impact analysis (A) is less relevant at this stage, while reviewing deliverables (C) does not address the inefficiencies, and seeking support from the project sponsor (D) may not provide a quick solution.