A supplier, who was tasked with providing an important component for a project, is unable to deliver the materials due to a large-scale labor problem. What document should the project manager use to update the details and communicate to relevant stakeholders?
Answer options
- A. Project schedule
- B. Issue log
- C. Risk register
- D. Change request
Correct answer: B
Explanation
The correct answer is B, Issue log, as it is specifically used to document and communicate problems that arise during a project. The project schedule focuses on timelines, the risk register addresses potential risks, and a change request is for formally requesting changes to the project scope, none of which directly address the current delivery issue.