Project Management Professional (PMP) — Question 818

Before a daily standup, a team member informed the project manager that they have accepted a job offer at another company. The team member explains that they plan to present their resignation to the functional manager.

What should the project manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because contacting the functional manager allows the project manager to proactively address the situation and develop a strategy to minimize disruption. Option A is irrelevant as it focuses on the sprint backlog rather than the personnel issue. Option B involves informing the team, which may not be appropriate at this stage. Option C is premature since the project manager should first assess the situation with the functional manager.