A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

Answer options

Correct answer: B

Explanation

The correct answer is B because creating a minimum viable product (MVP) allows for early testing of customer acceptance with limited resources. Option A suggests adding extra features, which may not address the core uncertainties. Option C would unnecessarily delay the project, and option D, while informative, does not directly address the need to evaluate customer acceptance.