Project Management Professional (PMP) — Question 793
During project execution, a client asks to add one more features to the product. After performing a change request analysis, the project manager realizes the necessary equipment will not be available in time to support this new feature, resulting in the project team being idle.
What should the project manager do next?
Answer options
- A. Establish a contingency reserve.
- B. Rent ready-made equipment.
- C. Escalate the risk to senior management.
- D. Perform integrated change control.
Correct answer: D
Explanation
The correct answer is D, as performing integrated change control allows the project manager to formally assess the impact of the requested change on the project. Options A and B do not address the need for formal approval and analysis of the change, while option C may not be necessary if the project manager can handle the change within the current project framework.