Project Management Professional (PMP) — Question 792
A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.
What should the project manager do?
Answer options
- A. Schedule a meeting and communicate the performance concern to the team.
- B. Hire a project team leader who can influence the project team members.
- C. Apply an agile approach to help improve team performance.
- D. Study and determine the appropriate leadership style suitable for the team.
Correct answer: D
Explanation
The correct answer is D because understanding the appropriate leadership style can significantly influence team dynamics and improve performance. Options A, B, and C may address symptoms of the problem but do not target the root cause of team commitment and effectiveness, which is best resolved through tailored leadership approaches.