Project Management Professional (PMP) — Question 785

A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.

What should the project manager do next?

Answer options

Correct answer: B

Explanation

The correct answer is B because updating the assumptions log and change log is crucial for maintaining accurate project documentation and initiating the change control process. This ensures that all stakeholders are aware of the changes and can make informed decisions. The other options do not adequately address the need to formally manage and document the changes to assumptions that impact the project's objectives.