Project Management Professional (PMP) — Question 785
A project scope was developed with numerous assumptions. During the execution phase, the assumptions changed, which has jeopardized the planned business value of the project.
What should the project manager do next?
Answer options
- A. Deliver what was planned in the project management document according to the specifications
- B. Update the assumptions log and change log, and implement the change control process
- C. Inform the client that the project cannot meet the project timeline and additional costs will be incurred
- D. Report on the changed assumptions to the project sponsor and seek support to prioritize the change requests
Correct answer: B
Explanation
The correct answer is B because updating the assumptions log and change log is crucial for maintaining accurate project documentation and initiating the change control process. This ensures that all stakeholders are aware of the changes and can make informed decisions. The other options do not adequately address the need to formally manage and document the changes to assumptions that impact the project's objectives.