Company A has a culture of adhering to policies and procedures. A project manager is applying an agile approach to their in-house software development project, but even with training, they are still unable to deliver efficiently.
What should the project manager do first to improve this situation?
Answer options
- A. Empower and coach the team members to focus on project delivery results.
- B. Identify key team members who can influence others to contribute efficiently.
- C. Follow company procedures and retrain team members on the agile approach.
- D. Ask company management to delay the project and grant it additional time.
Correct answer: A
Explanation
The correct answer is A because empowering and coaching team members fosters a collaborative environment that enhances focus on delivery outcomes, which is essential in agile practices. Options B, C, and D do not address the immediate need for team empowerment and may perpetuate inefficiencies or delay the project further.