Project Management Professional (PMP) — Question 780

A project manager has access to risk management tools but chooses to use a quantitative method to evaluate the project risks. During project execution, the project sponsor asks for an updated risk matrix.

What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because using integrated risk management software provides a systematic and comprehensive way to evaluate risks, ensuring all factors are considered. Option B is incorrect as it disregards the need for updating the risk assessment. Option C assumes that new risks should be added without proper evaluation, and option D relies solely on personal experience, which may not encompass all project risks.