Project Management Professional (PMP) — Question 77
The project manager has learned that the project sponsor is unhappy with the development of the project requirements.
In order to realign the project with the sponsor's expectations, what should the project manager do?
Answer options
- A. Review the project goal diagram with the team
- B. Perform a stakeholder evaluation
- C. Confirm which templates the team should be using
- D. Review the risk management plan
Correct answer: B
Explanation
The correct answer is B, as performing a stakeholder evaluation helps the project manager understand the sponsor's concerns and expectations better. The other options do not directly address the sponsor's dissatisfaction with the project requirements and focus on different aspects of project management.