Project Management Professional (PMP) — Question 767
A project manager has just been assigned to a new project. The project manager's first task is to present the project benefits to the stakeholders.
Which three items should form part of the presentation? (Choose three.)
Answer options
- A. Risks associated with achieving the target benefits
- B. Stakeholder register
- C. Communications management plan
- D. Expected business value
- E. Metrics to measure benefits throughout the project
Correct answer: A, D, E
Explanation
The correct answers A, D, and E are crucial as they outline potential risks, projected business value, and metrics for measuring benefits, providing a comprehensive view of the project's advantages. Options B and C, while important, do not directly pertain to the benefits of the project itself and are less relevant for this specific presentation.