Project Management Professional (PMP) — Question 764
Two project managers are working on separate projects that have identified the same subject matter expert (SME) as critical to their projects. Project A is using a predictive approach and Project B is using an agile approach.
Which project should the SME be allocated to?
Answer options
- A. The project with the less experienced project manager to improve the likelihood of success.
- B. The project with the highest score in the program to improve the likelihood of success.
- C. Project A, because project planning was based on the assumption that the SME would be available.
- D. Project B, because success in an agile project is determined by technical excellence.
Correct answer: B
Explanation
The correct answer is B because allocating the SME to the project with the highest score in the program maximizes the overall success potential. While Project A relies on the SME's availability as per its planning, Project B's agile nature allows for more flexibility, making it less critical than the overall program's success. Therefore, the other options do not prioritize the most impactful project.