Project Management Professional (PMP) — Question 743

A project team is finishing a sprint to deliver a key deliverable. The project team tells the project manager that the deliverable does not meet the agreed project standards set out by the customer and insists on reworking the deliverable to meet the standards. This will delay the project by two weeks.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A, as it emphasizes the importance of delivering a quality product that meets customer standards, despite the delay. Options B and C compromise the quality of the deliverable, which is against the project's goals. Option D, while addressing the issue with the sponsor, does not prioritize the immediate need to ensure the deliverable meets standards.