A client's company announces a reorganization, which includes changes in the senior management involved in the project. The new project sponsor is asking to put the project on hold until they review the scope.

What should the project manager do next?

Answer options

Correct answer: B

Explanation

The correct answer is B because engaging with the new project sponsor to discuss requirements and updating the project management plan ensures that the project aligns with the new leadership's vision. Answer A delays action without addressing the current project's needs, C involves the team without direct involvement from the new sponsor, and D focuses on risk rather than immediate project management alignment.