Project Management Professional (PMP) — Question 740
A client's company announces a reorganization, which includes changes in the senior management involved in the project. The new project sponsor is asking to put the project on hold until they review the scope.
What should the project manager do next?
Answer options
- A. Wait for a new project scope from the new project sponsor
- B. Discuss the requirements and update the project management plan with the new sponsor
- C. Discuss the issue with the project team and update the project management plan
- D. Amend the risk register and provide suggested mitigation strategies
Correct answer: B
Explanation
The correct answer is B because engaging with the new project sponsor to discuss requirements and updating the project management plan ensures that the project aligns with the new leadership's vision. Answer A delays action without addressing the current project's needs, C involves the team without direct involvement from the new sponsor, and D focuses on risk rather than immediate project management alignment.