A construction project to build a fish hatchery is in execution. The operations group notified the project manager about a concern that might turn into a potential issue; however, the concern could not be addressed.
In which project document should the project manager record the concern?
Answer options
- A. Request for information
- B. Scope statement
- C. Risk register
- D. Issue log
Correct answer: C
Explanation
The correct answer is C, the Risk register, as it is specifically designed to record potential risks and concerns that may impact the project. The other options do not serve this purpose; A is for clarifying information, B outlines the project's scope, and D is for documenting issues that have already occurred rather than potential concerns.