Project Management Professional (PMP) — Question 709
Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?
Answer options
- A. Update the stakeholder register.
- B. Consult the project sponsor.
- C. Refer to the resource management plan.
- D. Modify the statement of work (SOW).
Correct answer: C
Explanation
The correct answer is C, as the project manager should refer to the resource management plan to understand how to address the departure of the SME and manage resources effectively. Options A, B, and D do not directly address the immediate need to manage the project's resources and workforce planning following the loss of the SME.