Project Management Professional (PMP) — Question 708

During the execution phase of a project, one of the customer's stakeholders keeps requesting changes to the scope every week. Which three actions should the project manager take to resolve this issue? (Choose three.)

Answer options

Correct answer: A, B, E

Explanation

The correct actions involve updating documentation to reflect ongoing issues (A), discussing the implications of changes to ensure all stakeholders understand the impact (B), and aligning with the customer to clarify expectations and approach (E). Options C and D are not ideal as they either prematurely accept changes without proper discussion or ignore stakeholder input, which could lead to bigger issues down the line.